Project Scheduling with Time Windows and Scarce Resources VIII: A Vertex Schedule Maximizes the Net Present Value iff Its Spanning-Tree Subprojects Have the Right SignsTextbook
Long-running projects such as construction, plant engineering or software development involve payments to and from the contractor at many points in time: disbursements when activities are carried out, progress payments when milestones are reached. When the planning horizon is long, money received later is worth less, and the natural financial objective is…