Theorem 3.2.10 — antiactive, stable, semistable, pseudostable and quasistable schedules as maximal and extreme points
ProvedProjSchedTW.StableSchedules.stable_classes_extreme_pointsLet be the feasible region of a project with time windows, scarce renewable resources and deadline , and let be a feasible schedule. Then:
- (a) is antiactive if and only if is a maximal point of ;
- (b) is stable if and only if is an extreme point of ;
- (c) is semistable if and only if is an extreme point of a component of ;
- (d) is pseudostable if and only if is an extreme point of every order polytope belonging to a feasible strict order ;
- (e) is quasistable if and only if is an extreme point of the schedule polytope .
The five classes are defined through shifts: no global right-shift, and no pair of opposite global, local, order-monotone or order-preserving shifts. In symbols,
This is the counterpart for nonregular objectives of Theorem 2.4.9, which describes active schedules as minimal points. The finiteness results and the spanning-tree description of §3.2, and the classification of objective functions in §3.3, rest on it.
Formalization Note The component in (c) is the connected component of containing (Mathlib connectedComponentIn). Local shifts use continuous trajectories in . Connected and path components of coincide because is a finite union of polytopes (Theorem 2.3.7), but that is part of what has to be proved. Extreme points are Mathlib's Set.extremePoints ℝ. The feasibility of is a hypothesis: the book states the theorem for schedules of its classes, which are feasible by definition.
import Mathlib import Definitions.Def_ProjSchedTW_StableSchedules_Project import Definitions.Def_ProjSchedTW_StableSchedules_Shifts
namespace ProjSchedTW.StableSchedules
/-- Theorem 3.2.10 (p. 211). For a feasible schedule `S`:
(a) `S` is antiactive iff `S` is a maximal point of `𝒮`;
(b) `S` is stable iff `S` is an extreme point of `𝒮`;
(c) `S` is semistable iff `S` is an extreme point of a component of `𝒮` (necessarily the one
containing `S`);
(d) `S` is pseudostable iff `S` is an extreme point of every order polytope `S_T(O)` belonging
to a feasible strict order `O ⊆ O(S)`;
(e) `S` is quasistable iff `S` is an extreme point of the schedule polytope `S_T(O(S))`. -/
theorem stable_classes_extreme_points {n : ℕ} {K : Type} (P : Project n K)
(S : Fin (n + 2) → ℝ) (hS : S ∈ feasibleSet P) :
(IsAntiactive P S ↔ Maximal (· ∈ feasibleSet P) S) ∧
(IsStable P S ↔ S ∈ (feasibleSet P).extremePoints ℝ) ∧
(IsSemistable P S ↔ S ∈ (connectedComponentIn (feasibleSet P) S).extremePoints ℝ) ∧
(IsPseudostable P S ↔
∀ O : Set (Fin (n + 2) × Fin (n + 2)), IsFeasibleOrder P O → O ⊆ scheduleOrder P S →
S ∈ (orderPolytope P O).extremePoints ℝ) ∧
(IsQuasistable P S ↔ S ∈ (orderPolytope P (scheduleOrder P S)).extremePoints ℝ) := by sorry