p. 409 — the refined bound used in the 3-machine computations is a lower bound
ProvedIgnallSchrage.Makespan.refinedLowerBound_le_makespanbranch-and-boundflow-shoplower-boundp2o-batch-pfp2bp2o-gran-per-chapterp2o-plan-paperp2o-v1scheduling
Let be a node with jobs and any full sequence that begins with . Then the refined bound of p. 409, in which is replaced by and by , satisfies
The paper only reports that this bound "was used" in its computations; its use in branch and bound is valid exactly because it is still a lower bound, which is what this statement asserts.
Formalization Note The paper does not state the inequality explicitly; it is the property the use of the bound in the procedure requires. No sign condition on processing times is assumed.
Preamble
import Mathlib import Definitions.Def_IgnallSchrage_Makespan_RefinedLowerBound
Formal statement
namespace IgnallSchrage.Makespan
/-- p. 409: the refined bound used in the 3-machine computations is still a lower bound: for a
node `J = J_r` with `r < n` and every full sequence `σ` beginning with `J_r`, the refined bound
is at most the makespan of `σ`. -/
theorem refinedLowerBound_le_makespan {n : ℕ} (a b c : Fin n → ℝ) (J : List (Fin n))
(hJ : J.length < n) (σ : Equiv.Perm (Fin n)) (hσ : BeginsWith σ J) :
refinedLowerBound a b c J ≤ makespan a b c σ := by sorry
end IgnallSchrage.Makespan
Source
Ignall and Schrage, Application of the branch and bound technique to some flow-shop scheduling problems, Oper. Res. 13 (1965), p. 409, refined lower bound
Human review
Confirmed by the mission captain (proposal self-audit).
Confirmed by the moderator at approval.