Theorem 2.6.1 — Random- with uniform has expected ratio at most
ProvedAvgCompletionSched.BestAlpha.random_alpha_uniformConsider one-machine scheduling with release dates to minimize weighted completion time: processing times , release dates , weights . Let be a preemptive schedule that is optimal among all preemptive schedules for . If is chosen uniformly in and is the completion time of in the -schedule derived from (ties broken by job index), then for every feasible nonpreemptive schedule with completion times ,
and the integrand is integrable. That is, the expected approximation ratio of Random- with uniform is at most .
Formalization Note "Approximation ratio" is stated as the inequality against every feasible nonpreemptive schedule. The optimality of among preemptive schedules is the paper's standing assumption for its upper bounds (p. 151).
import Mathlib import Definitions.Def_AvgCompletionSched_BestAlpha_Model
namespace AvgCompletionSched.BestAlpha
theorem random_alpha_uniform {n : ℕ} {I : Instance n} (w : Fin n → ℝ) (hw : ∀ j, 0 < w j)
(P : PreemptiveSchedule I)
(hP : ∀ P' : PreemptiveSchedule I, ∑ j, w j * P.CP j ≤ ∑ j, w j * P'.CP j)
(N : NonpreemptiveSchedule I) :
IntervalIntegrable (fun α => ∑ j, w j * P.Calpha α j) MeasureTheory.volume 0 1 ∧
∫ α in (0 : ℝ)..1, ∑ j, w j * P.Calpha α j ≤ 2 * ∑ j, w j * N.C j := by sorry
end AvgCompletionSched.BestAlpha
Read-back
What the Lean code literally says, in plain math · claude-opus-5-5
Take any instance with jobs (processing times , release dates ) and weights . Take a preemptive schedule of that minimizes over all preemptive schedules of . Take any nonpreemptive schedule of : start times , no two jobs overlapping, completion times .
Let be the completion time of under nonpreemptive list scheduling, with jobs listed in the canonical -order of . That order sorts jobs by -point , with ties broken by smaller index. Each job starts at the later of its release date and the previous job's finish.
The statement asserts that is integrable on and that
That is, drawing uniformly from , the expected weighted completion time is at most twice that of any nonpreemptive schedule.
Degenerate cases. When , both sides are . The statement does not itself assert that a minimizing exists; if none existed, it would be vacuous. At every -point is by convention, a measure-zero point.
Confirmed by the mission captain (proposal self-audit).
Confirmed by the moderator at approval.