Theorem 4(a), claim (A): precedes
ProvedSchedComplexity.TotalCompletion.claim_Anp-completenessp2o-batch-pfp2bp2o-gran-per-chapterp2o-plan-paperp2o-v1schedulingtotal-completion-time
Let be positive integers with , and consider the instance and threshold of the construction of Theorem 4(a). In every feasible schedule with , every job outside is processed before every job of :
This is claim (A) of the converse direction: the long jobs of come last.
Formalization Note "Precedes" is read as "is processed earlier on the machine", i.e. starts earlier; there are no precedence constraints in this problem. Starting times are natural numbers (Section 3).
Preamble
import Mathlib import Definitions.Def_SchedComplexity_TotalCompletion_SingleMachine import Definitions.Def_SchedComplexity_TotalCompletion_Construction
Formal statement
namespace SchedComplexity.TotalCompletion
/-- Proof of Theorem 4(a), claim (A) (pp. 22–23): in every feasible schedule of the constructed
instance with `Σ_j C_j ≤ y`, every job outside `U` is processed before every job of `U`
(`{J_j | j ∉ U}` precedes `{J_j | j ∈ U}`), i.e. starts earlier. -/
theorem claim_A {t : ℕ} (a : Fin t → ℕ) (b : ℕ)
(ha : ∀ i, 0 < a i) (hb : 0 < b) (hbA : b < sumA a)
(B : Fin (numJobs a b) → ℕ)
(hB : IsFeasible (procTime a b) (release a b) B)
(hy : ∑ j, completion (procTime a b) B j ≤ yThreshold a b) :
∀ j' j : Fin (numJobs a b), j' ∉ groupU a b → j ∈ groupU a b → B j' < B j := by sorry
end SchedComplexity.TotalCompletion
Source
Brucker, Lenstra & Rinnooy Kan, Complexity of Machine Scheduling Problems, Mathematisch Centrum Report BW 43/75 (1975), p. 22 (statement) and p. 23 (proof), proof of Theorem 4(a), claim (A)