p. 408 — the 3-job example: 1–2 is optimal for jobs 1, 2, but 3–2–1 is the optimum for all three
ProvedIgnallSchrage.MeanCompletion.example_p408exampleflow-shopp2o-batch-pfp2bp2o-gran-per-chapterp2o-plan-paperp2o-v1scheduling
Take three jobs with processing times
| job | 1 | 2 | 3 |
|---|---|---|---|
| 2 | 10 | 1 | |
| 11 | 3 | 8 |
- For jobs 1 and 2 alone, the sequence 1–2 has sum of completion times and the sequence 2–1 has ; so 1–2 is optimal.
- For all three jobs, the sequence 3–2–1 has sum of completion times
and no full sequence has a smaller sum; so 3–2–1 is optimal and reverses the relative order of jobs 1 and 2.
The paper uses the example to explain why the solution of an -job subproblem helps little with the -job problem.
Formalization Note Jobs are 0-based in Lean: the paper's jobs 1, 2, 3 are 0, 1, 2. The sequence 3–2–1 is the permutation (positions 0, 1, 2 hold jobs 2, 1, 0) and 2–1 on two jobs is .
Preamble
import Mathlib import Definitions.Def_IgnallSchrage_MeanCompletion_Node
Formal statement
namespace IgnallSchrage.MeanCompletion
/-- p. 408, the 3-job example with `a = (2, 10, 1)`, `b = (11, 3, 8)` (jobs `1, 2, 3` of the
paper are `0, 1, 2` here). (i) For jobs 1 and 2 alone, the sequence 1–2 has sum of completion
times `29`, the sequence 2–1 has `37`, so 1–2 is optimal. (ii) For all three jobs, the
sequence 3–2–1 (`σ = (0 2)`: positions `0, 1, 2` hold jobs `2, 1, 0`) has sum `48` and is
optimal among all full sequences. -/
theorem example_p408 :
(totalCompletion (n := 2) ![2, 10] ![11, 3] 1 = 29 ∧
totalCompletion (n := 2) ![2, 10] ![11, 3] (Equiv.swap 0 1) = 37 ∧
∀ σ : Equiv.Perm (Fin 2),
totalCompletion (n := 2) ![2, 10] ![11, 3] 1 ≤ totalCompletion ![2, 10] ![11, 3] σ) ∧
(totalCompletion (n := 3) ![2, 10, 1] ![11, 3, 8] (Equiv.swap 0 2) = 48 ∧
∀ σ : Equiv.Perm (Fin 3),
totalCompletion (n := 3) ![2, 10, 1] ![11, 3, 8] (Equiv.swap 0 2) ≤
totalCompletion ![2, 10, 1] ![11, 3, 8] σ) := by sorry
end IgnallSchrage.MeanCompletion
Source
Ignall and Schrage, Application of the branch and bound technique to some flow-shop scheduling problems, Oper. Res. 13 (1965), p. 408, "Computational Results for M=2, Mean Completion Time", 3-job example