(15), p. 427 — optimal finishing time exceeds average total work
ProvedGrahamAnomaly.KLongest.sum_div_le_optFinishload-balancingmakespanp2o-batch-pfp2ap2o-gran-per-chapterp2o-plan-paperp2o-v1scheduling
Let be a positive number of identical processors and let be the lengths of finitely many tasks. If is the least finishing time over all assignments of these tasks, then
This is the average-load lower bound in the left half of Graham's display (15). It applies to every assignment, including an optimal one.
Formalization Note An empty task set is allowed here, in which case both sides are zero. The processor set is nonempty because .
Preamble
import Mathlib import Definitions.Def_GrahamAnomaly_KLongest_Model
Formal statement
namespace GrahamAnomaly.KLongest
theorem sum_div_le_optFinish {r n : ℕ} (hn : 0 < n) (μ : Fin r → ℝ)
(hμ : ∀ j, 0 < μ j) :
(1 / (n : ℝ)) * ∑ j, μ j ≤ optFinish μ n := by sorry
end GrahamAnomaly.KLongest
Source
Graham, Bounds on multiprocessing timing anomalies, SIAM J. Appl. Math. 17 (1969), p. 427, (15), left inequality