Lemma 4, p. 8 — the capacity of a minimum a-b-cut equals the value of an optimal solution of (1)–(5)
ProvedProjSchedMinCut.Transform.lemma_4minimum-cutp2o-batch-pfp2ap2o-gran-per-chapterp2o-plan-paperp2o-v1project-schedulingtime-indexed-formulation
Let be the minimum cut digraph of an instance of the project scheduling problem with start-time dependent costs , and assume a feasible schedule exists. Then has a minimum --cut, and for every minimum --cut there is an optimal solution of (1)–(5) with
Hence the scheduling problem with start-time dependent costs can be solved by a single minimum cut computation.
Formalization Note The existence of a minimum cut (the digraph is finite) is made explicit so that the statement is not vacuous. The capacity is compared with through the embedding of into ; in particular the minimum cut capacity is finite.
Preamble
import Mathlib import Definitions.Def_ProjSchedMinCut_Transform_Setting
Formal statement
namespace ProjSchedMinCut.Transform
open Instance
/-- Lemma 4, p. 8: a minimum `a`-`b`-cut of `D` exists, and the capacity of every minimum
`a`-`b`-cut equals the value `w(x)` of an optimal solution `x` of (1)–(5). -/
theorem lemma_4 {n : ℕ} (I : Instance n) (hw : ∀ j t, 0 ≤ I.w j t)
(hfeas : ∃ S, I.Feasible S) :
(∃ X, I.IsMinCut X) ∧
∀ X, I.IsMinCut X → ∃ x, I.IsOptimal x ∧ I.cutCap X = ENNReal.ofReal (I.cost x) := by sorry
end ProjSchedMinCut.Transform
Source
Möhring, Schulz, Stork & Uetz, Solving project scheduling problems by minimum cut computations, manuscript (July 2000, revised April 2002 and November 2002), p. 8, Lemma 4
Human review
Confirmed by the mission captain (proposal self-audit).
Confirmed by the moderator at approval.