Theorem 4(j) — KNAPSACK has a solution iff the three-machine job shop instance has C_max ≤ 2A
ProvedSchedComplexity.Shops.theorem_4j_equivalencejob-shopknapsacknp-completenessp2o-batch-pfp2bp2o-gran-per-chapterp2o-plan-paperp2o-v1scheduling
Let and be positive integers with , where . Consider the three-machine job shop with jobs: item job () has machine order and processing times ; has order and times , ; has order and times , . Then
This is the equivalence in the proof of Theorem 4(j), which shows that KNAPSACK reduces to .
Formalization Note The assumption and the positivity of the data are hypotheses. The equivalence is stated with "value " (p. 14).
Preamble
import Mathlib import Definitions.Def_SchedComplexity_OneMachine_Knapsack import Definitions.Def_SchedComplexity_Shops_Constructions
Formal statement
namespace SchedComplexity.Shops
/-- Theorem 4(j), Brucker, Lenstra & Rinnooy Kan, Report BW 43/75, p. 17: for positive integers
`a_1, …, a_t`, `b` with `0 < b < A = ∑ a_j`, KNAPSACK has a solution iff the three-machine job
shop `constrJ a b` (items with order `(M_1, M_3)` and times `a_j, a_j`; `J_{n-1}` with order
`(M_1, M_2)` and times `b, 2(A - b)`; `J_n` with order `(M_2, M_3)` and times `2b, A - b`) has a
feasible schedule with `C_max ≤ y = 2A`. -/
theorem theorem_4j_equivalence (a : List ℕ) (b : ℕ) (ha : ∀ v ∈ a, 0 < v) (hb : 0 < b)
(hbA : b < a.sum) :
SchedComplexity.OneMachine.KnapsackYes a b ↔ (constrJ a b).HasScheduleLE (yJ a) := by sorry
end SchedComplexity.Shops
Source
Brucker, Lenstra & Rinnooy Kan, Complexity of Machine Scheduling Problems, Mathematisch Centrum Report BW 43/75 (1975), p. 17, proof of Theorem 4(j)
Human review
Confirmed by the mission captain (proposal self-audit).
Confirmed by the moderator at approval.