Lemma 2.4 — some machine group has
ProvedFlowJobHardness.FlowShopGap.lemma_2_4flow-shopjob-shoplower-boundmakespanp2o-batch-pfp2bp2o-gran-per-chapterp2o-plan-paperp2o-v1
Let and be natural numbers and let be a feasible schedule of the flow shop instance whose makespan is less than . Then there is a machine group such that
where is the total time covered by the first halves of the good long-operations on machine .
With Lemma 2.3, this gives a single machine group whose first-half intervals are pairwise disjoint and have total length at least , which yields the lower bound of the main theorem.
Formalization Note The paper states Lemma 2.4 under the standing assumption of §2.2.2 (p. 20:10) that the schedule's makespan is less than ; it is an explicit hypothesis here. "For a sufficiently large " in the proof stands for , i.e. .
Preamble
import Mathlib import Definitions.Def_JobShopLTAS_Core_Instance import Definitions.Def_FlowJobHardness_FlowShopGap_Construction import Definitions.Def_FlowJobHardness_FlowShopGap_GoodOps open JobShopLTAS.Core
Formal statement
namespace FlowJobHardness.FlowShopGap
/-- Lemma 2.4 (p. 20:11), under the standing assumption of §2.2.2 that the makespan is less
than `r · lb`: for `r ≥ 8` and every feasible schedule of `F(r, d)` with makespan
`< r · r^{2d}`, some machine group `g ∈ {1, …, r^{2d}}` has
`∑_{f=1}^{d} L(T_{g,f}) ≥ (lb/4) · d`. -/
theorem lemma_2_4 (r d : ℕ) (hr : 8 ≤ r) (s : (inst r d).Op → ℝ)
(hs : (inst r d).IsFeasibleSchedule Finset.univ s)
(hmk : (inst r d).makespan Finset.univ s < (r : ℝ) * (r : ℝ) ^ (2 * d)) :
∃ g : ℕ, 1 ≤ g ∧ g ≤ r ^ (2 * d) ∧
(r : ℝ) ^ (2 * d) / 4 * (d : ℝ) ≤ ∑ f ∈ Finset.Icc 1 d, L r d s g f := by sorry
end FlowJobHardness.FlowShopGap
Source
Mastrolilli, Svensson, Hardness of Approximating Flow and Job Shop Scheduling Problems, J. ACM 58(5) (2011), Article 20, p. 20:11, Lemma 2.4 (standing assumption on p. 20:10)