(15), p. 427 — optimum controls the list finishing time minus residual imbalance
ProvedGrahamAnomaly.KLongest.optFinish_ge_sublist-schedulingload-balancingmakespanp2o-batch-pfp2ap2o-gran-per-chapterp2o-plan-paperp2o-v1scheduling
Under the independent-task list rule, suppose and the complete list finishes after the first tasks. Write for its finishing time, for the minimum finishing time over all assignments, and for the longest task after the prefix. For processors and positive task lengths,
This is the right inequality of Graham's display (15), together with the average-load comparison shown there.
Formalization Note The theorem states the resulting right inequality; the average-load left inequality is a separate milestone. Prefix optimality and longest-first order are not needed for this bound.
Preamble
import Mathlib import Definitions.Def_GrahamAnomaly_KLongest_Model
Formal statement
namespace GrahamAnomaly.KLongest
theorem optFinish_ge_sub {r n k : ℕ} (hn : 0 < n)
(μ : Fin r → ℝ) (hμ : ∀ j, 0 < μ j)
(L : Fin r ≃ Fin r) (σ : Fin r → Fin n)
(hσ : IsListAssignment μ L σ) (hkr : k < r)
(hgt : prefixFinish μ L σ k < WilliamsonShmoys.makespan μ σ) :
WilliamsonShmoys.makespan μ σ - ((n : ℝ) - 1) / n * alphaStar μ L k ≤
optFinish μ n := by sorry
end GrahamAnomaly.KLongest
Source
Graham, Bounds on multiprocessing timing anomalies, SIAM J. Appl. Math. 17 (1969), p. 427, proof of Theorem 3, (15), right inequality
Human review
Confirmed by the mission captain (proposal self-audit).
Confirmed by the moderator at approval.