Section 2.1, p. 291 — bounds the optimum makespan
ProvedJobShopLTAS.Core.optMakespan_le_m_mul_PmaxFor every job shop instance with machines,
This places the optimum inside the horizon on which the intervals of the first type and the linear program of the paper are defined.
Formalization Note. The statement carries no hypotheses: it holds for every instance, including and assumed in Section 2.1.
import Mathlib import Definitions.Def_JobShopLTAS_Core_Instance
namespace JobShopLTAS.Core
/-- §2.1, p. 291: "`m P_max` is an upper bound on the length of an optimum schedule." -/
theorem optMakespan_le_m_mul_Pmax {m n : ℕ} (inst : Instance m n) :
inst.optMakespan Finset.univ ≤ (m : ℝ) * inst.Pmax := by sorry
end JobShopLTAS.Core
Read-back
What the Lean code literally says, in plain math · claude-opus-5-5
Setup. Take any natural numbers and any job-shop instance, with no further hypotheses. The instance consists of:
- machines and jobs;
- job has operations , ;
- operation runs on machine with real processing time .
Let be the load of machine , and .
A schedule gives each operation a real start . It is feasible when:
- all starts are ;
- for every job and every with : ;
- distinct operations on the same machine do not overlap: one ends no later than the other starts.
The makespan of a schedule is , or if there are no operations. Let be the infimum of the makespans of all feasible schedules.
Claim.
Degenerate cases.
- If , the right-hand side is , and by the empty-supremum convention. No job can have an operation, since there is no machine, so and the claim is .
- If , or all , then and all loads are , so the claim is .
- If the set of feasible makespans were empty, would take the default value .
Confirmed by the mission captain (proposal self-audit).
Confirmed by the moderator at approval.