Proposition 1 (C+), p. 11, restated p. 12 — Φ^C+ = {0}, with negotiated terms p = 0, β = 1
ProvedProjectOutsourcing.SingleTask.prop1_costplusUnder the standing assumptions of Section 3,
- : the cost-plus contract coordinates the system exactly when the client has full bargaining power, ;
- at every solution of Problem B (3) under C+ has the terms
that is, the client covers all of the subcontractor's cost and pays nothing more.
The cost-plus contract is one of the two most common contract forms in practice; this statement says that it coordinates the project only in the extreme case where the client has all the bargaining power.
Formalization Note The second coordinate of a C+ term is a dummy fixed at the printed value (C+ is CS with ). Under C+ with the subcontractor is indifferent among work rates; footnote 1's tie-break (he chooses the system-optimal rate) is part of the model, and it is what makes coordination at possible. For every feasible C+ outcome gives the subcontractor zero profit, so every feasible outcome solves Problem B, including non-coordinating ones; this is why is excluded.
import Mathlib import Definitions.Def_ProjectOutsourcing_SingleTask_Setting
namespace ProjectOutsourcing.SingleTask
theorem prop1_costplus (M : Model) (hM : M.Valid) :
Phi M .Cplus = {0} ∧ (∀ x, IsNashSol M .Cplus 0 x → x.1 = (0, 1)) := by sorry
end ProjectOutsourcing.SingleTask