Proof of Lemma 9 — along the finishing order
ProvedFlowJobShop.SPT.work_lower_boundjob-shoplower-boundmean-flow-timep2o-batch-pfp2bp2o-gran-per-chapterp2o-plan-paperp2o-v1scheduling
Let a job shop with processors and jobs be given, the total task time of job , and any feasible non-preemptive schedule. Let be an order in which the jobs finish in , that is, a bijection with . Then for every ,
Equivalently , where is the finishing order. This is the first lower-bound step of the proof of Lemma 9, applied there to an OMFT schedule ; it holds for every feasible schedule.
Formalization Note Positions are 0-based and the inequality is multiplied by , so no division by occurs. Feasibility allows zero-time tasks to occupy no processor interval. The paper assumes .
Preamble
import Mathlib import Definitions.Def_JobShopLTAS_Core_Instance import Definitions.Def_FlowJobShop_SPT_MeanFlowTime open JobShopLTAS.Core
Formal statement
namespace FlowJobShop.SPT
/-- Let `τ` be any feasible non-preemptive schedule of an `m`-processor job shop, and let
`ρ 0, ρ 1, …` be the order in which the jobs finish in `τ` (finish times nondecreasing).
Then for every `k`, `m · f_{ρ k}(τ) ≥ ∑_{j ≤ k} L_{ρ j}` (Gonzalez–Sahni 1978, proof of Lemma 9,
p. 47: `f_{i_k}(S*) ≥ ∑_{j=1}^k L_{i_j}/m`, multiplied by `m`). -/
theorem work_lower_bound {m n : ℕ} (inst : Instance m n) (hm : 0 < m) (τ : inst.Op → ℝ)
(hτ : IsPaperFeasibleSchedule inst τ) (ρ : Fin n ≃ Fin n)
(hρ : Monotone fun k => finishTime inst τ (ρ k)) (k : Fin n) :
∑ j ∈ Finset.Iic k, inst.jobLength (ρ j) ≤ (m : ℝ) * finishTime inst τ (ρ k) := by sorry
end FlowJobShop.SPT
Source
Gonzalez, Sahni, Flowshop and Jobshop Schedules: Complexity and Approximation, Operations Research 26(1) (1978), p. 47, §2, proof of Lemma 9 ('For S* we have f_{i_k}(S*) ≥ Σ_{j=1}^k L_{i_j}/m')