Lemma 3, p. 8 — the image under (7) of a finite-capacity n-cut is feasible for (1)–(5), with w(x) = c(X, X̄)
ProvedProjSchedMinCut.Transform.lemma_3minimum-cutn-cutp2o-batch-pfp2ap2o-gran-per-chapterp2o-plan-paperp2o-v1project-schedulingtime-indexed-formulation
Let be the minimum cut digraph of an instance of the project scheduling problem with start-time dependent costs , and assume a feasible schedule exists. For each -cut of of finite capacity, the mapping (7) defines a feasible solution of the integer program (1)–(5), and
Together with Lemma 2 and the injectivity of (7), this gives the one-to-one correspondence of Theorem 1.
Formalization Note Feasibility includes the window convention of p. 4 (variables outside vanish). The capacity is compared with through the embedding of into .
Preamble
import Mathlib import Definitions.Def_ProjSchedMinCut_Transform_Setting
Formal statement
namespace ProjSchedMinCut.Transform
open Instance
/-- Lemma 3, p. 8: for each finite-capacity `n`-cut `(X, X̄)` of `D`, the mapping (7) defines a
feasible solution `x` of (1)–(5) with `w(x) = c(X, X̄)`. -/
theorem lemma_3 {n : ℕ} (I : Instance n) (hw : ∀ j t, 0 ≤ I.w j t)
(hfeas : ∃ S, I.Feasible S) :
∀ X, I.IsNCut X → I.cutCap X < ⊤ →
I.IPFeasible (I.xOfCut X) ∧ I.cutCap X = ENNReal.ofReal (I.cost (I.xOfCut X)) := by sorry
end ProjSchedMinCut.Transform
Source
Möhring, Schulz, Stork & Uetz, Solving project scheduling problems by minimum cut computations, manuscript (July 2000, revised April 2002 and November 2002), p. 8, Lemma 3